The building is heated and cooled with a thermally active floor slab. For this purpose there is a reversible heat pump.

Building owner

Apparatebau Kirchheim-Teck GmbH

Finalization

2019

Heating demand

41,9 kWh/m²a

Architecture
Special planning
ZAB
c
Thermal activated building
Thermal activated building
Heating + Cooling
Heating + Cooling

The building is heated and cooled with a thermally active floor slab. For this purpose there is a reversible heat pump which gets the heat and cold from 11 geothermal probes with 150 m depth. A photovoltaic system is installed on the greened flat roof for the company's own electricity needs.

ZAB
Ingenieurplanung Söllner
ZAB
Ingenieurplanung Söllner